Notice Details

TSP Name

Great Lakes Gas Transmission Limited Partnership

Notice ID

1210

TSP

046077343

Notice Eff Date:

08/04/2026

Posting Date/Time:

08/04/2026 11:48

Notice End Date:

11/01/2026

Critical:

Yes

Notice Eff Time:

11:53

Notice Type:

Plnd Outage

Notice End Time:

08:59

Notice Status:

Supersede

Required Response:

No response required

Prior Notice ID:

1208

Response Date/Time:

Subject

MAINTENANCE SCHEDULE for Great Lakes Gas Transmission (Posted: 8/4/26)

Message Text

Great Lakes Gas Transmission Maintenance Schedule has been updated.

 

Please refer to the maintenance schedule for the projected capacity impacts. Updated items are as follows: 

 

  • Thief River Falls Station 2 to MLV 2-1 dig (100-line) capacity adjustment
  • Date Change on some of the scheduled digs, due to permitting issues 
  • Date Change – Iron River Station 6 A-line Valve Replacement from previous dates of 9/29 - 10/5 to new dates 9/22 – 9/28
  • Add – Pipe Replacement MLV 3-2 to 3-3 (100-line) on 9/29 – 10/5

 

 

Please note that the information posted is proposed and subject to change.

 

Please direct any questions to your Account Coordinator, Customer Service Representative, or the Nominations and Scheduling hotline @ 866-454-7572.