TSP Name

Great Lakes Gas Transmission Limited Partnership

Notice ID

1020

TSP

046077343

Notice Eff Date:

03/27/2025

Posting Date/Time:

03/27/2025 08:31

Notice End Date:

11/01/2025

Critical:

Yes

Notice Eff Time:

08:35

Notice Type:

Plnd Outage

Notice End Time:

08:59

Notice Status:

Supersede

Required Response:

No response required

Prior Notice ID:

1018

Response Date/Time:

Subject

MAINTENANCE SCHEDULE for Great Lakes Gas Transmission (Posted: 3/27/25)

Message Text

Great Lakes Gas Transmission Maintenance Schedule has been updated.

 

Please refer to the maintenance schedule for the projected capacity impacts.  Updated items are as follows:  

 

• Remove – Farwell Station 12 TSA Required Automation Upgrade/Panel Replacement on 4/14 – 6/27 (moved to 2026 execution)

• Add – Crystal Falls Station 8 ESD Test and Coolers Demolition on 4/29 – 5/3

• Date Change – Iron River Unit 602 Exhaust Silencer Replacement, previously scheduled for 5/6 – 5/16 to new dates of 5/1 – 5/22

• Add – Farwell Station 12 Air Compressor Replacement on 5/5 – 5/16

• Date Change – Shevlin Station 3 TSA Required Automation Upgrade previously scheduled for 5/6 – 8/15 to new dates of 5/29 – 9/5

• Date Change – Cloquet Unit 502 Check Valve and Discharge Valve Replacement previously scheduled for 5/26 – 6/6 to new dates of 6/10 – 6/23

• Date Change – Wakefield Station 7 TSA Required Automation Upgrade/Panel Replacement, previously scheduled for 6/3 – 9/12 to new dates of    6/17 – 9/26

• Date Change – Sta 2 to Sta 3 MFL Tool Run (100-line) previously scheduled for 6/20 to new date of 7/10

• Add – Deer River Unit 401 Lube Oil Pump Replacement on 7/21 – 7/30

• Date Change – Iron River Station 6 Fire and Gas Detection Equipment Replacement and Valve Replacements, previously scheduled for 9/23 –      10/13 to new dates of 10/2 – 10/24

 

Please direct any questions to your Account Coordinator, Customer Service Representative, or the Nominations and Scheduling hotline @ 866-454-7572.